The assumptions necessary for a successful product-oriented layout include all EXCEPT which of the following?


A) adequate volume for high equipment utilization
B) standardized product
C) volatile product demand
D) adequately standardized supplies of raw materials and components
E) All of the above are appropriate assumptions.

F) A) and E)
G) C) and D)

Correct Answer

verifed

verified

Departments A,B,C,and D need to be assigned to four rooms 1,2,3,and 4.These rooms are arranged in a row,in that order,with 20 meters between each.The departmental work flows are contained in the table below. (a)What is the material handling total of assigning A-1,B-2,C-3,D-4? (b)What is the material handling total of assigning A-1,B-3,C-4,D-2? Departments A,B,C,and D need to be assigned to four rooms 1,2,3,and 4.These rooms are arranged in a row,in that order,with 20 meters between each.The departmental work flows are contained in the table below. (a)What is the material handling total of assigning A-1,B-2,C-3,D-4? (b)What is the material handling total of assigning A-1,B-3,C-4,D-2?

Correct Answer

verifed

verified

(a)The material handling total of A-1,B-...

View Answer

Which of the following reduces product handling,inventory,and facility costs,but requires both (1) tight scheduling and (2) accurate inbound product information?


A) phantom-docking
B) random stocking
C) ASRS
D) customizing
E) cross-docking

F) A) and E)
G) None of the above

Correct Answer

verifed

verified

A product-oriented layout would be MOST appropriate for which one of the following businesses?


A) fast food
B) steel making
C) insurance sales
D) clothing alterations
E) a grocery store

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

A firm operates a flow shop building kitchen cabinetry for recreational vehicles.The major activities of this process are listed below. A firm operates a flow shop building kitchen cabinetry for recreational vehicles.The major activities of this process are listed below.    a.Draw the appropriate network for this project. b.What would the cycle time be if the goal is to produce 20 units per month (the plant operates 160 hours per month)? c.What is the theoretical minimum number of workstations needed? d.Balance with the most following tasks heuristic.What tasks are assigned to which stations? e.What is the efficiency of the line obtained in part d? a.Draw the appropriate network for this project. b.What would the cycle time be if the goal is to produce 20 units per month (the plant operates 160 hours per month)? c.What is the theoretical minimum number of workstations needed? d.Balance with the most following tasks heuristic.What tasks are assigned to which stations? e.What is the efficiency of the line obtained in part d?

Correct Answer

verifed

verified

blured image blured image (b)The cycle time is 160/20 = 8 hours;...

View Answer

________ is the maximum time that the product is allowed at each workstation.

Correct Answer

verifed

verified

An airport is trying to balance where to place the three subgroups (local (A),regional (B),and national (C))for an airline.The distance between terminals and the number of trips that travelers make between subgroups for flight connections per day are listed.Find the assignment that minimizes the distance travelers must walk. An airport is trying to balance where to place the three subgroups (local (A),regional (B),and national (C))for an airline.The distance between terminals and the number of trips that travelers make between subgroups for flight connections per day are listed.Find the assignment that minimizes the distance travelers must walk.

Correct Answer

verifed

verified

There are 6 possible assignments and the...

View Answer

What is a servicescape? How is it related to the retail layout problem? What are the three elements of servicescape for dealing with these human issues?

Correct Answer

verifed

verified

Servicescape describes the physical surr...

View Answer

The concept of customizing in a warehouse layout:


A) is possible,but it causes serious loss of oversight of the quality function.
B) cannot be considered seriously in today's high efficiency factories.
C) is theoretically sound,but several years away in practice.
D) incorporates value-added activities in warehouses.
E) locates stock wherever there is an open location.

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

________ refers to the physical surroundings in which a service takes place,and how they affect customers and employees.

Correct Answer

verifed

verified

One of the major advantages of process-oriented layouts is:


A) high equipment utilization.
B) large work-in-process inventories.
C) flexibility in equipment and labor assignment.
D) smooth and continuous flow of work.
E) small work-in-process inventories.

F) A) and D)
G) None of the above

Correct Answer

verifed

verified

One guideline for a retail layout is to locate high-draw items around the periphery of the store.

A) True
B) False

Correct Answer

verifed

verified

One drawback of a product-oriented layout is that work stoppage at any one point ties up the whole operation.

A) True
B) False

Correct Answer

verifed

verified

Which of the following does NOT support the retail layout objective of maximizing customer exposure to products?


A) Locate high-draw items around the periphery of the store.
B) Use prominent locations for high-impulse and high-margin items.
C) Maximize exposure to expensive items.
D) Use end-aisle locations.
E) Convey the store's mission with the careful positioning of the lead-off department.

F) A) and D)
G) A) and E)

Correct Answer

verifed

verified

What design guidelines help retail layouts to maximize customer exposure to products?

Correct Answer

verifed

verified

1.Locate the high-draw items around the ...

View Answer

Four hundred and eighty minutes of production time are available per day.The schedule calls for the production of 80 units per day.Each unit of the product requires 30 minutes of work.What is the theoretical minimum number of workstations?


A) 2
B) 3
C) 4
D) 5
E) 6

F) A) and D)
G) All of the above

Correct Answer

verifed

verified

The major problem addressed by the warehouse layout strategy is:


A) minimizing difficulties caused by material flow varying with each product.
B) requiring frequent close contact between forklift drivers and item pickers.
C) addressing trade-offs between space and material handling.
D) balancing product flow from one work station to the next.
E) locating the docks near a convenient access point to the closest highway.

F) A) and E)
G) A) and C)

Correct Answer

verifed

verified

Deloitte & Touche solved the empty desk problem by:


A) assigning permanent desks.
B) implementing a "hoteling" program.
C) creating open offices.
D) no longer allowing employees to work from home.
E) reducing the number of allowable sick days per employee.

F) A) and C)
G) All of the above

Correct Answer

verifed

verified

The work cell layout,a special arrangement of machinery and personnel to focus on the production of a single product or group of related products,is for manufacturing applications and has no relevance to services.

A) True
B) False

Correct Answer

verifed

verified

Workspace can inspire informal and productive encounters if it balances what three physical and social aspects?


A) proximity,privacy,and persuasion
B) privacy,persuasion,and permission
C) proximity,privacy,and permission
D) proximity,persuasion,and permission
E) proximity,persuasion,and passion

F) A) and E)
G) B) and E)

Correct Answer

verifed

verified

Showing 41 - 60 of 145