A ___________ Gantt chart is a simple and effective way to depict progress on a project.


A) baseline
B) control
C) variance
D) tracking
E) simple

F) None of the above
G) A) and E)

Correct Answer

verifed

verified

All projects need some form of formal control. Agree or disagree? Support you answer.

Correct Answer

verifed

verified

Control by "wandering around" and / or "...

View Answer

The value that tells you the planned value of work that has actually been completed is the


A) SV.
B) PV.
C) EV.
D) AC.
E) CV.

F) A) and B)
G) C) and D)

Correct Answer

verifed

verified

The final step in the project control process for measuring and evaluating project performance is to


A) take appropriate action.
B) prepare a report to top management.
C) follow up on corrective action.
D) measure progress and performance.
E) review spending with team members.

F) A) and D)
G) B) and D)

Correct Answer

verifed

verified

A CPI index of 1.18 indicates that the project is currently ________ schedule.


A) ahead of
B) behind
C) over
D) under
E) cannot be determined.

F) A) and C)
G) A) and E)

Correct Answer

verifed

verified

Because of their easy-to-understand visual format, ________ charts are the most favored, used, and understandable tool used to report project schedule status.


A) Network
B) Work breakdown structure
C) Gantt
D) Burndown
E) Cost / schedule

F) B) and E)
G) None of the above

Correct Answer

verifed

verified

The only accurate method for determining the true time progress of the project is to compare the project network schedule against the actual network schedule to measure if the project is on time.

A) True
B) False

Correct Answer

verifed

verified

Given that the AC = 500, PV = 400 and EV = 300, this project is currently _________ budget and ______ schedule.


A) under, ahead of
B) under, behind
C) over, behind
D) over, ahead of
E) on, on

F) A) and C)
G) D) and E)

Correct Answer

verifed

verified

Although it is very difficult to measure, measuring ________ performance is as important as measuring schedule and cost performance.


A) procurement
B) technical
C) stakeholder
D) human resources
E) risk

F) A) and B)
G) C) and D)

Correct Answer

verifed

verified

Which of the following methods will measure the cost efficiency of the work accomplished to date?


A) SV / CV
B) EV / PV
C) EV / AC
D) AC / SV
E) AC / CV

F) None of the above
G) C) and E)

Correct Answer

verifed

verified

C

The first step in the project control process for measuring and evaluating project performance is to


A) set a baseline plan.
B) determine the project objectives.
C) determine the project deliverables.
D) analyze the project budget.
E) review the project priority matrix.

F) B) and C)
G) A) and D)

Correct Answer

verifed

verified

A

________ is simply the percent complete times the original budget.


A) Actual cost
B) Earned value
C) Cost Performance Index
D) Schedule Performance Index
E) Budget at Completion

F) A) and B)
G) All of the above

Correct Answer

verifed

verified

Which of the following is NOT true regarding scope creep?


A) It commonly occurs late in projects.
B) It is frequently unnoticed until time delays or cost overruns are observed.
C) It wears down team motivation and cohesiveness.
D) Project suppliers resent frequent changes.
E) Scope changes can represent significant opportunity.

F) B) and E)
G) All of the above

Correct Answer

verifed

verified

A

A reason that the duration on a task may differ from an original duration on a tracking Gantt chart could be


A) an expected delay.
B) new information on the task.
C) the task has been cancelled.
D) a new budget cycle.
E) an unexpected delay.

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

The PV, AC and CV are all required to assess the current status of the project.

A) True
B) False

Correct Answer

verifed

verified

The ________ rule assumes credit is earned for having performed the work once it is completed. This rule is usually used for work packages having very short durations.


A) one-to-ten
B) one-to-one
C) 50 / 100
D) 0 / 100
E) 50 / 50

F) A) and C)
G) None of the above

Correct Answer

verifed

verified

The indicator that tells you the amount each remaining dollar must earn for the project to stay within budget is the


A) PCIC.
B) VAC.
C) CPI.
D) SPI.
E) TCPI.

F) C) and D)
G) B) and D)

Correct Answer

verifed

verified

Because of their easy-to-understand visual format, tracking Gantt charts are the most favored, used, and understandable option for reporting project status.

A) True
B) False

Correct Answer

verifed

verified

The ________ variance is the difference between the earned value to date and the baseline schedule.


A) schedule
B) cost
C) budget
D) time
E) performance

F) B) and D)
G) All of the above

Correct Answer

verifed

verified

Baseline project budgets are derived from time-phasing the work ________.


A) products
B) milestones
C) packages
D) modules
E) resources

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified