Which of the following is the net requirement using an MRP program if the gross requirement is 1,250 and the inventory on hand is 50?


A) 1,200
B) 1,300
C) 1,150
D) 2,450
E) None of these

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

We would expect to see which of the following in an MRP system's inventory status file?


A) End items produced
B) Late/early delivery records
C) Scrap parts
D) Labor efficiency
E) Computer errors

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

A product tree can do which of the following?


A) Help to compute component usage.
B) Reduce product scrap.
C) Reduce labor overtime.
D) Reduce regular time labor.
E) Locate raw material supplies.

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

Which of the following can be used for lot sizing in an MRP system?


A) Low-level coding
B) Time bucket size
C) Least unit cost
D) Inventory record file
E) Peg inventory

F) A) and C)
G) None of the above

Correct Answer

verifed

verified

Which of the following is a dynamic lot-sizing technique that calculates the order quantity by comparing the carrying cost and the setup (or ordering) costs for various lot sizes and then selects the lot size in which these are most nearly equal?


A) Kanban
B) Just-in-time system
C) MRP
D) Least unit cost
E) Least total cost

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

Which of the following is an input file necessary to run an MRP system?


A) Bill of materials (BOM) file
B) Quality management report
C) Exception reports
D) Planned-order schedules
E) Purchasing contracts

F) A) and C)
G) A) and D)

Correct Answer

verifed

verified

The time-phased plan specifying how many and when the firm plans to build each end item is called the master production schedule (MPS).

A) True
B) False

Correct Answer

verifed

verified

True

Which of the following is considered a secondary report in an MRP system?


A) Planned order schedule
B) Exceptions reports
C) Inventory record
D) Firm orders from known customers
E) Engineering change reports

F) None of the above
G) C) and D)

Correct Answer

verifed

verified

B

MRP is based on dependent demand.

A) True
B) False

Correct Answer

verifed

verified

The MRP program performs its analysis from the bottom up of the product structure trees, imploding requirements level by level.

A) True
B) False

Correct Answer

verifed

verified

A master production schedule is an input to a material requirements planning (MRP) system.

A) True
B) False

Correct Answer

verifed

verified

Which of the following industry types have high expected benefits from the application of MRP?


A) Fabricate-to-order
B) Hospitals
C) Assemble-to-order
D) Aircraft manufacturers
E) Oil refineries

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

Which of the following is a dynamic lot-sizing technique that adds ordering and inventory carrying cost for each trial lot size and divides by the number of units in each lot size, picking the lot size with the lowest unit cost?


A) Economic order quantity
B) Lot-for-lot
C) Least total cost
D) Least unit cost
E) Inventory item averaging

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified

Net change MRP reflects the exact status of each item managed by the system in "real time."

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not a lot-sizing technique used in MRP systems?


A) Lot-for-lot (L4L)
B) Economic order quantity (EOQ)
C) Least total cost (LTC)
D) Least unit cost (LUC)
E) Warehouse loading factor (WLF)

F) B) and E)
G) D) and E)

Correct Answer

verifed

verified

An input to the material requirements planning (MRP) system is an exception report.

A) True
B) False

Correct Answer

verifed

verified

Which of the following files allows us to retrace a material requirement upward in the product structure through each level, identifying each parent item that created the demand?


A) Planning bill of materials file
B) Modular bill of materials file
C) Super bill of materials file
D) Exception report file
E) Peg record file

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Which of the following is an input to the master production schedule?


A) Prototype products from product development
B) Aggregate component schedule
C) Peg reports
D) Exception reports
E) Forecasts of random demand from customers

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Which of the following is a dynamic lot-sizing technique that calculates the order quantity by comparing the carrying cost and the setup (or ordering) costs for various lot sizes and then selects the lot in which these are most nearly equal?


A) Economic order quantity
B) Lot-for-lot
C) Least total cost
D) Least unit cost
E) ABC analysis

F) B) and E)
G) None of the above

Correct Answer

verifed

verified

Which of the following is the net requirement using an MRP program if the gross requirement is 1,000 and the inventory on hand is 500?


A) 1,000
B) 950
C) 500
D) 400
E) 350

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

C